400 ROCK PEAK DR, Henderson, NV
26 open permits
37 permits have been filed at 400 ROCK PEAK DR since 2023, involving 8 applicants. 26 remain open and 11 have been closed.
37
Total Permits
26
Open
11
Closed
8
Applicants
Permit Type Breakdown
Structural7 rated
0.0% closed vs 78% median, 77.6 points lower
Commercial2 rated
0.0% closed vs 94% median, 93.6 points lower
Residential1 rated
0.0% closed vs 88% median, 87.5 points lower
Median based on all applicants with 20+ rated permits. Only permits older than 1 year are rated.
Applicants at This Address
All Permits
37 permits
| Status | Permit # | Address | Issued▼ | ||||
|---|---|---|---|---|---|---|---|
| Open | Fire - Suppression/Extinguishing Systems | 400 ROCK PEAK DR, Henderson | COSCO FIRE PROTECTION INC | May 21, 2026<1yr | — | — | |
| Closed | BLDG - Report | 400 ROCK PEAK DR, Henderson | COSCO FIRE PROTECTION INC | May 16, 2026<1yr | May 16, 2026 | — | |
| Open | Fire - Suppression/Extinguishing Systems | 400 ROCK PEAK DR, Henderson | COSCO FIRE PROTECTION INC | May 6, 2026<1yr | — | — | |
| Closed | BLDG - Report | 400 ROCK PEAK DR, Henderson | COSCO FIRE PROTECTION INC | Apr 20, 2026<1yr | Apr 20, 2026 | — | |
| Closed | BLDG - Report | 400 ROCK PEAK DR, Henderson | COSCO FIRE PROTECTION INC | Apr 20, 2026<1yr | Apr 20, 2026 | — | |
| Open | Fire - Suppression/Extinguishing Systems | 400 ROCK PEAK DR, Henderson | COSCO FIRE PROTECTION INC | Mar 16, 2026<1yr | — | — | |
| Closed | BLDG - Report | 400 ROCK PEAK DR, Henderson | SUFFOLK CONSTRUCTION COMPANY INC | Mar 5, 2026<1yr | Mar 5, 2026 | — | |
| Open | BLDG - Certificate of Occupancy | 400 ROCK PEAK DR, Henderson | SUFFOLK CONSTRUCTION COMPANY INC | Jan 22, 2026<1yr | — | — | |
| Open | Fire - Suppression/Extinguishing Systems | 400 ROCK PEAK DR, Henderson | Residential Fire Protection | Nov 26, 2025<1yr | — | — | |
| Closed | Fire - Suppression/Extinguishing Systems | 400 ROCK PEAK DR, Henderson | Sep 10, 2025<1yr | Sep 10, 2025 | — | ||
| Closed | BLDG - Report | 400 ROCK PEAK DR, Henderson | Sep 8, 2025<1yr | Sep 8, 2025 | — | ||
| Open | BLDG - Non-Building Structure | 400 ROCK PEAK DR, Henderson | POWER DESIGN INC | Aug 20, 2025<1yr | — | — | |
| Open | BLDG - Commercial Building | 400 ROCK PEAK DR, Henderson | GIBERTI CONSTRUCTION LLC | Aug 19, 2025<1yr | — | $20,000 | |
| Open | BLDG - Commercial Building | 400 ROCK PEAK DR, Henderson | SUFFOLK CONSTRUCTION COMPANY INC | Aug 7, 2025<1yr | — | $8,540,550 | |
| Open | BLDG - Commercial Building | 400 ROCK PEAK DR, Henderson | SUFFOLK CONSTRUCTION COMPANY INC | Aug 7, 2025<1yr | — | $7,876,100 | |
| Open | BLDG - Multi-Fam Residential | 400 ROCK PEAK DR, Henderson | SUFFOLK CONSTRUCTION COMPANY INC | Aug 7, 2025<1yr | — | $17,761,244.95 | |
| Open | BLDG - Multi-Fam Residential | 400 ROCK PEAK DR, Henderson | SUFFOLK CONSTRUCTION COMPANY INC | Aug 7, 2025<1yr | — | $20,388,687.75 | |
| Open | BLDG - Commercial Building | 400 ROCK PEAK DR, Henderson | SUFFOLK CONSTRUCTION COMPANY INC | Jul 28, 2025<1yr | — | $337,650 | |
| Closed | BLDG - Report | 400 ROCK PEAK DR, Henderson | Residential Fire Protection | Jul 24, 2025<1yr | Jul 24, 2025 | — | |
| Open | PW - Civil Improvements | 400 ROCK PEAK DR, Henderson | WESTWOOD PROFESSIONAL SERVICES | Jul 14, 2025<1yr | — | — | |
| Closed | PW - Civil Improvements | 400 ROCK PEAK DR, Henderson | WESTWOOD PROFESSIONAL SERVICES | May 5, 2025 | May 5, 2025 | — | |
| Open | BLDG - Residential MP&E | 400 ROCK PEAK DR, Henderson | POWER DESIGN INC | Mar 28, 2025 | — | — | |
| Open | BLDG - Multi-Fam Residential | 400 ROCK PEAK DR, Henderson | SUFFOLK CONSTRUCTION COMPANY INC | Jan 21, 2025 | — | $3,730,200 | |
| Closed | Fire - Suppression/Extinguishing Systems | 400 ROCK PEAK DR, Henderson | Jan 8, 2025 | Jan 8, 2025 | — | ||
| Open | Fire - Blasting | 400 ROCK PEAK DR, Henderson | SANDERS CONSTRUCTION, INC. | Sep 3, 2024 | — | — | |
| Closed | BLDG - Report | 400 ROCK PEAK DR, Henderson | Mar 4, 2024 | Mar 4, 2024 | — | ||
| Open | BLDG - Commercial Building | 400 ROCK PEAK DR, Henderson | SUFFOLK CONSTRUCTION COMPANY INC | Jan 30, 2024 | — | $450,000 | |
| Closed | BLDG - Report | 400 ROCK PEAK DR, Henderson | Jan 25, 2024 | Jan 25, 2024 | — | ||
| Open | PW - Civil Improvements | 400 ROCK PEAK DR, Henderson | WESTWOOD PROFESSIONAL SERVICES | Jan 22, 2024 | — | — | |
| Open | Fire - Blasting | 400 ROCK PEAK DR, Henderson | SANDERS CONSTRUCTION, INC. | Dec 26, 2023 | — | — | |
| Open | BLDG - Wall | 400 ROCK PEAK DR, Henderson | TARGET CONSTRUCTION INC. | Sep 18, 2023 | — | $801.18 | |
| Open | BLDG - Wall | 400 ROCK PEAK DR, Henderson | TARGET CONSTRUCTION INC. | Aug 19, 2023 | — | $543.68 | |
| Open | BLDG - Wall | 400 ROCK PEAK DR, Henderson | TARGET CONSTRUCTION INC. | Aug 15, 2023 | — | $503.22 | |
| Open | BLDG - Wall | 400 ROCK PEAK DR, Henderson | TARGET CONSTRUCTION INC. | Jul 18, 2023 | — | $1,777.18 | |
| Open | BLDG - Wall | 400 ROCK PEAK DR, Henderson | TARGET CONSTRUCTION INC. | Jul 18, 2023 | — | $1,102.18 | |
| Open | BLDG - Wall | 400 ROCK PEAK DR, Henderson | TARGET CONSTRUCTION INC. | Jul 18, 2023 | — | $832.18 | |
| Open | BLDG - Wall | 400 ROCK PEAK DR, Henderson | TARGET CONSTRUCTION INC. | Jul 18, 2023 | — | $1,102.18 |