3740 05th Av, San Diego, CA
31 open permits
41 permits have been filed at 3740 05th Av since 2021, involving 8 applicants. 31 remain open and 10 have been closed.
41
Total Permits
31
Open
10
Closed
8
Applicants
Applicants at This Address
| Applicant | Permits | Open |
|---|---|---|
| SKYLINE CAPITAL BUILDERS | 21 | 21 |
| peter hayden | 6 | 0 |
| TAD Excavation | 5 | 5 |
| ACS Construction | 3 | 3 |
| innovative fire protection | 1 | 0 |
| Katie York | 1 | 0 |
| Dante Gomez | 1 | 0 |
All Permits
41 permits
| Status | Permit # | Address | Issued▼ | ||||
|---|---|---|---|---|---|---|---|
| Closed | PMT-3353545 | Approval - Construction - Fire Pmt - Alarm | 3740 05th Av, San Diego | peter hayden | May 27, 2025<1yr | Dec 15, 2025 | — |
| Closed | PMT-3354154 | Approval - Construction - Fire Pmt - Suppression | 3740 05th Av, San Diego | peter hayden | May 27, 2025<1yr | Dec 15, 2025 | — |
| Closed | PMT-3340495 | Electrical Pmt | 3740 05th Av, San Diego | peter hayden | Apr 21, 2025<1yr | Dec 15, 2025 | — |
| Closed | PMT-3340456 | Building Permit | 3740 05th Av, San Diego | peter hayden | Apr 21, 2025<1yr | Dec 15, 2025 | $88,296 |
| Closed | PMT-3340496 | Mechanical Pmt | 3740 05th Av, San Diego | peter hayden | Apr 21, 2025<1yr | Dec 15, 2025 | — |
| Closed | PMT-3340497 | Plumbing Pmt | 3740 05th Av, San Diego | peter hayden | Apr 21, 2025<1yr | Dec 15, 2025 | — |
| Open | PMT-3297497 | Traffic Control Permit | 3740 05th Av, San Diego | ACS Construction | Jun 28, 2024 | — | — |
| Open | PMT-3292639 | Traffic Control Permit | 3740 05th Av, San Diego | ACS Construction | May 28, 2024 | — | — |
| Open | PMT-3281584 | Traffic Control Permit | 3740 05th Av, San Diego | ACS Construction | Apr 10, 2024 | — | — |
| Open | PMT-3278486 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Mar 20, 2024 | — | — |
| Open | PMT-3258992 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Dec 22, 2023 | — | — |
| Open | PMT-3249019 | Alternate Methods and Materials | 3740 05th Av, San Diego | Dec 18, 2023 | — | — | |
| Open | PMT-3248522 | Alternate Methods and Materials | 3740 05th Av, San Diego | Dec 18, 2023 | — | — | |
| Open | PMT-3243406 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Oct 4, 2023 | — | — |
| Open | PMT-3224327 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Aug 23, 2023 | — | — |
| Open | PMT-3237022 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Aug 3, 2023 | — | — |
| Open | PMT-3233024 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Jul 11, 2023 | — | — |
| Open | PMT-3223674 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Jun 8, 2023 | — | — |
| Open | PMT-3210661 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Apr 19, 2023 | — | — |
| Open | PMT-3213429 | Traffic Control Permit | 3740 05th Av, San Diego | TAD Excavation | Apr 12, 2023 | — | — |
| Open | PMT-3211332 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Mar 23, 2023 | — | — |
| Open | PMT-3208444 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Mar 7, 2023 | — | — |
| Open | PMT-3202938 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Feb 27, 2023 | — | — |
| Open | PMT-3203622 | Traffic Control Permit | 3740 05th Av, San Diego | TAD Excavation | Feb 16, 2023 | — | — |
| Open | PMT-3196158 | Traffic Control Permit | 3740 05th Av, San Diego | TAD Excavation | Jan 20, 2023 | — | — |
| Open | PMT-3192197 | Traffic Control Permit | 3740 05th Av, San Diego | TAD Excavation | Dec 19, 2022 | — | — |
| Open | PMT-3193220 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Dec 14, 2022 | — | — |
| Open | PMT-3188760 | Traffic Control Permit | 3740 05th Av, San Diego | TAD Excavation | Nov 29, 2022 | — | — |
| Open | PMT-3182519 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Oct 28, 2022 | — | — |
| Open | PMT-3177589 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Sep 27, 2022 | — | — |
| Open | PMT-3167620 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Aug 29, 2022 | — | — |
| Open | PMT-3156712 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Jun 8, 2022 | — | — |
| Open | PMT-3154822 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | May 19, 2022 | — | — |
| Open | PMT-3154824 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | May 19, 2022 | — | — |
| Open | PMT-3133292 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Jan 18, 2022 | — | — |
| Open | PMT-3132385 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Jan 18, 2022 | — | — |
| Closed | PMT-3116234 | Approval - Construction - Fire Pmt - Suppression | 3740 05th Av, San Diego | Katie York | Jan 12, 2022 | Jan 12, 2024 | — |
| Closed | PMT-3120254 | Approval - Construction - Fire Pmt - Underground | 3740 05th Av, San Diego | innovative fire protection | Dec 7, 2021 | Apr 16, 2023 | — |
| Closed | PMT-3114530 | Approval - Construction - Fire Pmt - Alarm | 3740 05th Av, San Diego | Dante Gomez | Oct 8, 2021 | Oct 8, 2023 | — |
| Open | PMT-3097584 | Traffic Control Permit | 3740 05th Av, San Diego | SKYLINE CAPITAL BUILDERS | Apr 27, 2021 | — | — |
| Closed | PMT-3095433 | Approval - Construction - Demolition Pmt | 3740 05th Av, San Diego | Apr 9, 2021 | Oct 6, 2021 | — |