4220 N US HWY 421, Wilmington, NC, 28401
1 open permit
31 permits have been filed at 4220 N US HWY 421 since 2021, involving 15 applicants. 1 remains open and 30 have been closed.
31
Total Permits
1
Open
30
Closed
15
Applicants
Permit Type Breakdown
Building12 rated
100.0% closed vs 99% median, 0.7 points higher
Median based on all applicants with 20+ rated permits. Only permits older than 1 year are rated.
Applicants at This Address
All Permits
31 permits
| Status | Permit # | Address | Issued▼ | ||||
|---|---|---|---|---|---|---|---|
| Closed | Building | 4220 N US HWY 421, Wilmington | Oct 22, 2024 | Dec 10, 2024 | $0 | ||
| Closed | Building | 4220 N US HWY 421, Wilmington | Aug 13, 2024 | Feb 20, 2025 | $0 | ||
| Closed | Building | 4220 N US HWY 421, Wilmington | Odyssey Fire Protection | Jun 24, 2024 | Dec 3, 2024 | $0 | |
| Closed | Building | 4220 N US HWY 421, Wilmington | Sentinel Security Systems Inc | Dec 22, 2023 | Jan 26, 2024 | $0 | |
| Closed | Mechanical | 4220 N US HWY 421, Wilmington | Southeastern Heating Air & Electrical | Dec 1, 2023 | Jan 25, 2024 | $0 | |
| Closed | Building | 4220 N US HWY 421, Wilmington | MCKINLEY BUILDING CORP | Nov 23, 2022 | Nov 22, 2022 | $0 | |
| Open | Mechanical | 4220 N US HWY 421, Wilmington | Odyssey | Nov 14, 2022 | — | $0 | |
| Closed | Electrical | 4220 N US HWY 421, Wilmington | THE SIGN COMPANY OF WILMINGTON | Oct 21, 2022 | Oct 27, 2022 | $0 | |
| Closed | Electrical | 4220 N US HWY 421, Wilmington | MCKINLEY BUILDING CORP | Aug 24, 2022 | Aug 25, 2022 | $9,210,453.54 | |
| Closed | Electrical | 4220 N US HWY 421, Wilmington | Coates Electric of Wilmington Inc | Aug 4, 2022 | Apr 11, 2024 | $0 | |
| Closed | Electrical | 4220 N US HWY 421, Wilmington | Sentinel Security Systems Inc | Jun 29, 2022 | Aug 31, 2022 | $9,210,453.54 | |
| Closed | Electrical | 4220 N US HWY 421, Wilmington | UHL INC | Jun 29, 2022 | Jul 11, 2022 | $0 | |
| Closed | Building | 4220 N US HWY 421, Wilmington | UHL INC | May 24, 2022 | Jul 18, 2022 | $5,061,601.79 | |
| Closed | Building | 4220 N US HWY 421, Wilmington | Odyssey Fire Protection | May 24, 2022 | Jun 16, 2022 | $5,061,601.79 | |
| Closed | Plumbing | 4220 N US HWY 421, Wilmington | Uhl, Inc. | May 2, 2022 | Jul 11, 2022 | $5,061,601.79 | |
| Closed | Mechanical | 4220 N US HWY 421, Wilmington | Uhl, Inc. | May 2, 2022 | Jul 8, 2022 | $5,061,601.79 | |
| Closed | Electrical | 4220 N US HWY 421, Wilmington | Uhl, Inc. | Apr 29, 2022 | Jul 15, 2022 | $5,061,601.79 | |
| Closed | Building | 4220 N US HWY 421, Wilmington | UHL INC | Apr 19, 2022 | Sep 29, 2022 | $5,061,601.79 | |
| Closed | Building | 4220 N US HWY 421, Wilmington | Mar 25, 2022 | Aug 31, 2022 | $0 | ||
| Closed | Electrical | 4220 N US HWY 421, Wilmington | Coates Electric of Wilmington Inc | Feb 28, 2022 | Aug 31, 2022 | $9,210,453.54 | |
| Closed | Plumbing | 4220 N US HWY 421, Wilmington | Signature Plumbing | Feb 25, 2022 | Aug 31, 2022 | $9,210,453.54 | |
| Closed | Mechanical | 4220 N US HWY 421, Wilmington | ODYSSEY MECHANICAL LLC | Feb 25, 2022 | Nov 18, 2022 | $9,210,453.54 | |
| Closed | Building | 4220 N US HWY 421, Wilmington | MCKINLEY BUILDING CORP | Feb 16, 2022 | Nov 29, 2022 | $9,210,453.54 | |
| Closed | Electrical | 4220 N US HWY 421, Wilmington | MCKINLEY BUILDING CORP | Nov 15, 2021 | Nov 17, 2021 | $0 | |
| Closed | Electrical | 4220 N US HWY 421, Wilmington | SENTINEL SECURITY SYSTEMS INC | Nov 12, 2021 | Dec 16, 2021 | $0 | |
| Closed | Mechanical | 4220 N US HWY 421, Wilmington | Southeastern Heating and Air | Jun 30, 2021 | Aug 31, 2021 | $13,465,957.35 | |
| Closed | Electrical | 4220 N US HWY 421, Wilmington | MCKINLEY BUILDING CORP | Jun 23, 2021 | Dec 14, 2021 | $13,465,957.35 | |
| Closed | Plumbing | 4220 N US HWY 421, Wilmington | McKinley Building Corporation | Jun 14, 2021 | Feb 2, 2022 | $13,465,957.35 | |
| Closed | Building | 4220 N US HWY 421, Wilmington | FUNSTON CONSTRUCTION COMPANY LLC | Jun 11, 2021 | Dec 21, 2021 | $0 | |
| Closed | Plumbing | 4220 N US HWY 421, Wilmington | MCKINLEY BUILDING CORP | Mar 18, 2021 | Sep 2, 2021 | $13,465,957.35 | |
| Closed | Building | 4220 N US HWY 421, Wilmington | MCKINLEY BUILDING CORP | Mar 12, 2021 | Feb 3, 2022 | $13,465,957.35 |